Our team have been busy patching up a failing tidal pool.
As the cost of a complete rebuild was prohibitive, Our client instructed us to undertake some emergency patch repairs.
Access to the site is restricted, so we decided to use our 13m long reach excavator and a small boat skip to move materials and equipment to the work area when the tides permitted.
Timber shuttering was constructed on site and approx. 3m3 of ready-mix concrete was placed via wheelbarrows to reconstruct the damaged corner.